Iron Ore Pelletizing Plant, Gudesheng Metals Limited, Inner Mongolia Autonomous Region, China
1×12㎡豎爐工程及輔助設(shè) / 施基本設(shè)計(jì),詳細(xì)設(shè)計(jì),施工服務(wù)及調(diào)試 / 2012
Shaft Furnace:1×12㎡ and Support System / Engineering & Design,Supervision during Construction,Erection & Commissioning / 2012
Zhengda Iron & Steel Co. Limited,China
2×10㎡豎爐工程及輔助設(shè)施 /基本設(shè)計(jì),詳細(xì)設(shè)計(jì),施工服務(wù)及調(diào)試/ 2009
Shaft Furnace:2×10㎡& Support / Engineering & Design,Supervision during Construction,Erection & Commissioning / 2009
Zhengda Iron & Steel Co. Limited,China
No.5 2×12㎡豎爐工程及輔助設(shè)施 / 基本設(shè)計(jì),詳細(xì)設(shè)計(jì),軟件編程,相關(guān)技術(shù)服務(wù)文件 / 2009
No.5 Shaft Furnace:2×12㎡& Support / Engineering & Design, Supervision during Construction, Erection & Commissioning / 2009
Iron Ore Pelletizing Plant, MSPL, India under E + P Contract with Sinosteel MECC,China
120萬噸/年鏈篦機(jī)-回轉(zhuǎn)窯球團(tuán)廠工程 / 基本設(shè)計(jì),詳細(xì)設(shè)計(jì),軟件編程,相關(guān)技術(shù)服務(wù)文件 / 2008~2012
Grate + Kiln Pelletizing Plant having Capacity of 1,200,000 t/a / Engineering & Design,Supervision during Construction, Erection & Commissioning / 2008~2012
China Railways Equip. Materials & Supplies Limited,Cangzhou,Hebei,China
1×180㎡燒結(jié)機(jī)工程及輔助設(shè)施 / 總承包工程,包括:基本設(shè)計(jì),詳細(xì)設(shè)計(jì),供貨,施工,安裝,調(diào)試投產(chǎn) / 2012~2013
SP:1×180㎡ & Support system / EPC Contract including Engineering / Design,Supply,Construction,Erection,Testing & Commissioning / 2012~2013
China Railways Equip. Materials & Supplies Limited,Cangzhou,Hebei,China
1×260㎡燒結(jié)機(jī)工程及輔助設(shè)施 / 總承包工程包括:基本設(shè)計(jì),詳細(xì)設(shè)計(jì),供貨,施工,安裝,調(diào)試投產(chǎn) / 2011
SP:1×260㎡ & Support system / EPC Contract including Engineering / Design, Supply, Construction, Erection, Testing & Commissioning / 2011
TJK-Sino Steels Limited
煉鋼、軋鋼、連鑄項(xiàng)目(年產(chǎn)量15萬噸)/ 詳細(xì)設(shè)計(jì),施工服務(wù)及調(diào)試 / 2011~2013
Engaged in steel making, concasting and steel rolling(Capacity of 150,000 t/a) / Design, Supervision during Construction, Erection & Commissioning / 2011~2013
Wantong Saw Pipes Limited, Qianxi,Hebei,China
3#1×120㎡步進(jìn)式燒結(jié)機(jī)工程及輔助設(shè)施 / 基本設(shè)計(jì),詳細(xì)設(shè)計(jì),施工服務(wù)及調(diào)試 / 2011
SP :No. 3,1×120㎡(Hydro -Driven)& Support System / Engineering & Design,Supervision during Construction,Erection & Commissioning / 2011
Wantong Saw Pipes Limited,Qianxi,Hebei,China
1×120㎡步進(jìn)式燒結(jié)機(jī)改造工程及輔助設(shè)施 / 基本設(shè)計(jì),詳細(xì)設(shè)計(jì),施工服務(wù)及調(diào)試 / 2009
SP:1×120㎡(Hydro -Driven)& Support System (Revamping) / Engineering & Design,Supervision during Construction,Erection & Commissioning / 2009
Zhongte New Chemical & Energy Technology Co. Limited,Hubei,China
1×265㎡燒結(jié)機(jī)工程及輔助設(shè)施 / 基本設(shè)計(jì),詳細(xì)設(shè)計(jì),施工服務(wù)及調(diào)試 / 2009~2011
SP:1×265㎡ & Support System / Engineering & Design,Supervision during Construction,Erection & Commissioning / 2009~2011